Toilet Provision Project
At the general meeting held on the 26th April the association voted in favour of investigating the provision of a toilet on the site. This would be a compost toilet. Peta Carter volunteered to be the project manager. The project is still in its early days but please visit this page for updates.
14/06/2010
Peta submiited her first project progress report to the committee which included plans for the key stages of the project.
16/06/2010
The association secretary sent a letter to Preston City Council asking for permission in principle for the provision of a toilet on the site subject to further investigation.